Once the project mandate has been approved (Gate 1), the Project Manager can commence detailed planning of the project.
This is an important phase within the project as it determines the preferred approach along with the key milestones, deliverables, activities and resources (people and money), and the project benefits including success measures.
This includes:
If the project requires the procurement of a system, it is important that key requirements are captured and reviewed by IT during the business case development, and attached to the business case as an appendix.
Project objectives should be a short statement describing the positive change the project aims to make. They should define the desired benefits, outcomes or performance improvements that the project expects to deliver.
Objectives can be outputs, such as the delivery of a new system or a new building; outcomes, such as all teams being trained to use a new system, or moving a team in to a new building; or benefits, such as increased turn over due to new system, or reduced building costs as a result of the new building.
Project objectives should not describe what you plan to do or how you plan to do it.
Objective: Reduce spending on printer paper by 50% by December.
Project objectives should be presented in the following format:
“To (improve / increase / reduce / enhance) something, by (amount) (£ / %), by (date)".
The business case (.docx) sets out the reasons why the project is required and should give full consideration to the nature, organisation and implementation of the project including how it will contribute towards the achievement of our University’s strategic objectives.
The business case will consider the following key areas:
All relevant stakeholders must have been consulted with, for example if the project requires IT services resource, the project manager must work in conjunction with the subject matter expert in IT Services to determine realistic timescales for delivery of activity or products and obtain agreement that the resources are secured.
The business case should be created during the Stage 2 planning phase and once approved, maintained throughout the lifecycle of the project. This allows the business case to act as a key reference point and provide an audit trail of approved decision making.
The privacy impact assessment (.docx) should be used in conjunction with the business case template.
Once the business case (.docx) is developed it should be shared with the Project Sponsor for approval before it is submitted to its respective sub-group.
The sub-groups have two roles at this stage:
PCG may make one of three decisions when considering a business case:
If the project budget is greater than the amount approved at Gate 1 (approval of the project mandate) the business case will be endorsed by PCG to the appropriate committee for consideration for approval.
It is the responsibility of the secretary of PCG to inform Project Managers and Project Sponsors in writing of the decision made by the authorising committee.